How to Brief an Electrical Subcontractor: An RFQ Checklist
A good request for quotation tells an electrical subcontractor what to install, to which drawings and rules, with how many people, by when and with which documents at the end – and asks for the evidence you need before anyone arrives on site. This checklist covers each part and ends with questions for the first call.
01 / Article
An electrical subcontractor can only price and plan what it understands. A short but complete request for quotation (RFQ) saves rounds of questions, makes offers comparable and avoids disputes about what was included. The checklist below is written for procurement, project and site managers who subcontract electrical installation, machine connection or relocation work on industrial projects. It does not cover rates or contract law.
What should the scope description contain?
Describe the work in a way that someone who has never seen the site can follow:
- Type of work: for example cable tray installation, cable pulling, terminations, machine connection, control cabinet wiring, temporary site power, relocation of a line, testing and commissioning support.
- Quantities: approximate cable lengths, number of cabinets, machines or connection points.
- Inclusions and exclusions: who supplies material, who supplies tools and lifting equipment, who does the testing, who programs the PLC.
- Interfaces: where the work of other trades ends and the electrical scope begins, for example the machine builder, the mechanical contractor or the rigging company.
- Site: address, type of facility (production, cleanroom, construction site), working hours and access restrictions.
Which drawings and documents should go with the request?
- layouts and cable routes;
- schematics, cable lists and terminal plans;
- the bill of materials, if the subcontractor supplies material;
- your labelling standard and documentation template;
- the plant's specifications, for example preferred cable types or gland systems.
State the revision of each document and how changes will be communicated. A list of open design points is better than an offer based on assumptions.
Which standards and site rules apply?
Tell the subcontractor which standards and internal specifications the work must follow and which site rules apply. Typical items:
- required safety certificates, for example SCC or VCA, and whether company or personnel certificates are expected (see SCC, VCA and SGU explained);
- site induction, permit-to-work and lockout procedures;
- personal protective equipment beyond the basics, for example for cleanrooms;
- rules for working at height, hot work and lifting equipment;
- who carries out and signs the final inspection and tests.
What team do you need, and which languages?
- the number of electricians and helpers per phase, and whether a foreman or site lead is required;
- the qualifications expected, for example experience with control cabinets, drives or cleanroom work;
- the language for instructions, documentation and safety briefings;
- shift patterns and expected overtime;
- who arranges accommodation, transport and tools.
What evidence should you request?
Ask for documents with the offer or at the latest before mobilisation, so that nobody is turned away at the gate:
- Safety certificates: company and/or personnel certificates as required by the site, with names and validity dates.
- Electrical qualifications of the people who will work on site.
- Liability insurance: insurer, amount per claim and per year, and whether the policy covers the type of work, for example installation or relocation.
- Tax and registration documents where relevant: for construction services in Germany, the client is generally required to withhold 15 % of the payment unless the contractor presents an exemption certificate under Section 48b of the German Income Tax Act (EStG) or another exception applies (Section 48 EStG).
- Posting documents: if workers are sent from another country, ask which documents and registrations the subcontractor will provide for the country of work.
- References from comparable projects, ideally with photographs.
How should the schedule be set out?
- requested start date and the latest acceptable start date;
- duration of each phase, with milestones such as cabinets set, cables pulled, terminations complete, tests passed;
- dependencies on other trades and on deliveries;
- planned shutdown windows, if the work takes place in a running plant;
- how often progress is reported, and to whom.
Which documentation and handover do you expect?
- marked-up drawings and cable lists showing the as-installed state;
- test records with measured values and the instruments used;
- photographs of key stages, if required;
- a list of open points with an owner and date;
- the format for all of this (paper, PDF, your template) and the deadline.
Questions for the first call
- Have you done comparable work, and can you show photographs or references?
- How quickly can you mobilise, and with how many people?
- Who will be our contact on site, and which language does the team use?
- Which certificates and insurance documents can you send before mobilisation?
- What do you need from us to start: drawings, materials, access, power?
- How do you document cables and terminations during the work?
- How do you handle changes to the scope during the project?
- What tools and test equipment does the team bring?
What Onezone can provide
Onezone s.r.o. from Žilina works as an electrical subcontractor on industrial projects in Europe and the USA. Depending on the project, we can deploy qualified professionals within a few days, and no later than within two weeks. In each two-person team at least one member has the necessary language skills; fully multilingual teams are available on request. Our certifications page shows the SCC / SGU certificate, liability insurance of €2,000,000 per claim (Allianz) and electrical qualifications; completed projects are on the references page. Services: electrician teams in Europe and industrial electrical installation. Send your RFQ via the contact page.
Frequently asked questions
What is the minimum an electrical RFQ should include?
A scope description with inclusions and exclusions, the current drawings or cable lists, the site location and rules, the required start date and duration, and the documents you expect at handover.
Which documents should I request from a foreign electrical subcontractor?
Typically safety certificates required on site, electrical qualifications of the team, proof of liability insurance, references, and the tax and posting documents relevant for the country of work. For construction services in Germany, a client generally has to withhold tax from the payment unless an exemption certificate under Section 48b EStG is presented (Section 48 EStG).
When should certificates and insurance documents be checked?
Before mobilisation, ideally with the offer. Checking names and validity dates in advance avoids delays at the site gate.
Should the RFQ specify the team language?
Yes. State the language for instructions, documentation and safety briefings, and whether every team member or only the team lead needs to speak it.
Sources
- Gesetze im Internet – § 48b EStG, Freistellungsbescheinigung (exemption from withholding on construction services; checked 20 November 2026) gesetze-im-internet.de
- SSVV – VCA company certification and Central Certificate Register (checked 20 November 2026) ssvv.nl
- VAZ e.V. – Validity of SCC-VAZ certificates and SGU personnel certificates (checked 20 November 2026) vaz-ev.de
- Gesetze im Internet – § 48 EStG, Steuerabzug bei Bauleistungen (15 % withholding by the recipient of construction services; checked 20 November 2026) gesetze-im-internet.de
02 / Related
Read on
Related services
03 / Contact
Contact Us Today
Our experienced team of electricians, mechanics, and technicians is ready to support your project with expertise and precision. Trust your electrical installation and assembly needs to professionals who prioritize quality, reliability, and a tailored approach. Contact us today!
- Samuel Stas, B.Sc. Owner & CEO
Responsible for international projects, client relations, and the coordination of our technical teams across Europe and the USA.
- Matúš Židuliak, B.Sc. Owner & CEO
Responsible for company strategy, business development, turnkey projects in Slovakia and the Czech Republic, and communication with clients.
- Martin Miksa Sales Representative
Responsible for communication with customers and business partners, as well as coordinating projects in Germany and Austria.