Electrical Checklist for Relocating a Production Line or CNC Machine

The electrical side of a relocation succeeds or fails before the first cable is cut: survey and document the existing wiring, label every conductor, disconnect safely, agree the interface with the riggers, then reconnect, test and hand over against the same records. This checklist walks through each step for production lines and individual CNC machines.

Published Publisher Onezone s.r.o.

Dismantled parts of the REIS welding line on pallets in a hall

01 / Article

A production line or CNC machine can be moved electrically without surprises if four things are in place: a survey that captures the wiring as it really is, labels that survive transport, a clear split of work with the rigging contractor, and a test and handover routine at the new site. The steps below follow that order. They are written for project managers and site managers who plan the move and subcontract the electrical work.

For machines in Europe, the commonly applied reference for the electrical equipment is IEC/EN 60204-1, Safety of machinery – Electrical equipment of machines – Part 1: General requirements. According to the IEC, whose webstore lists the 2016 edition as of 20 November 2026, it covers the electrical equipment of machines from the point where the supply is connected. The machine builder's documentation and the plant's own rules remain the first reference for what applies to your equipment.

What should be surveyed before anything is disconnected?

Start with a walk-down of the line together with the plant's maintenance staff and, if available, the machine builder. The aim is to know what exists, not what the drawings say should exist.

  • Drawings against reality: compare schematics and cabinet layouts with the installed state. Mark undocumented modifications, temporary bridges and spare cores in use.
  • Supply data: record the feeding point, voltage, protective devices and cable cross-sections for each cabinet and machine, so the new site can be prepared in time.
  • Interfaces between machines: list every cable that runs between machines, conveyors, robots and cabinets, including fieldbus, network and safety circuits such as emergency stop chains and door interlocks.
  • Control data: the plant or machine builder should back up PLC programs, drive parameters, robot programs and network addresses. This is not electrical installation work, but without it the reconnection cannot be completed.
  • Other media: note compressed air, cooling water and extraction connections that share routes or cabinets with electrical cables.
  • Photographs: take systematic photos of terminal strips, connectors and cable entries before any work starts. They are the quickest reference during reconnection.

The result is a cable schedule: one line per cable, with its identifier, source, destination, type and whether it stays with the machine or is cut and re-terminated.

How should cables and terminals be labelled?

Labels are the link between the old and the new site, so they need to survive dismantling, packing, sea or road freight and storage.

  • Label both ends of every cable that is disconnected, with the same identifier as in the cable schedule.
  • Use the existing identifiers from the drawings where they exist; add a consistent project prefix where they do not.
  • Mark connectors and their counterparts, not only the cables.
  • Record which cables are left connected inside a machine module and travel as one unit.
  • Keep one master copy of the schedule and photographs, and share it with everyone who will reconnect.

How is the line disconnected safely?

Disconnection follows the plant's isolation procedure. Typical points to agree in advance:

  • who switches off and locks out each feed, and who verifies that the equipment is dead before work starts;
  • stored energy, for example in drive DC links, capacitors and uninterruptible power supplies, and the waiting times stated by the manufacturer;
  • which feeds must stay live for the rest of the plant;
  • how cut or disconnected cable ends are insulated, coiled and protected;
  • how open cabinets are closed, braced and protected against moisture and dust for transport.

Where does the electrical work meet rigging and transport?

Most relocations involve a rigging or machine-moving company and sometimes the machine builder. Write down the interface before the first day on site:

  • the sequence in which modules are released by the electricians and lifted by the riggers;
  • who removes cable trays, trunking and cables that are fixed to the building;
  • how cables that stay on a module are fixed so that they are not crushed during lifting;
  • who records damage found after transport, and how it is reported.

What happens at the new site?

Reconnection starts before the line arrives. The new supply points, cable routes and protective earthing should be ready and checked against the survey data. Then:

  • set and level the machines, then route and fix cables along the new paths;
  • re-terminate each cable according to the schedule and photographs, and tick it off;
  • replace damaged cables or connectors rather than repairing them provisionally;
  • record every deviation from the original wiring, for example longer cables or a changed route.

How is the relocated line tested and commissioned?

Testing should prove that the line is safe and that it works as before. The exact test scope comes from the machine documentation, the applicable standards and the plant's procedures. A typical sequence:

  • visual inspection of terminations, glands and cable fixing;
  • continuity of protective conductors and bonding;
  • insulation resistance of power circuits;
  • phase sequence and direction of rotation of motors;
  • checks of emergency stop, door interlocks and other safety functions;
  • input and output checks, then a functional run together with the plant, the machine builder or the integrator.

Results are written down with the instrument used, date and name of the tester.

Which documents belong in the handover?

  • the updated cable schedule and marked-up drawings showing the as-installed state;
  • test records with measured values;
  • a list of replaced cables and components;
  • open points with an owner and a date;
  • a signed handover note that states what was handed over and in what condition.

How we approach relocations

Onezone s.r.o. from Žilina works as an electrical subcontractor for the dismantling, relocation and reinstallation of CNC machines and production lines. References include the relocation of a REIS CNC welding line between two sites for Thermic Energy GmbH near Leipzig, a vaccine production line moved from Germany to the USA, and a CNC machine for automotive drive shafts that was dismantled, moved, reassembled and professionally cleaned. Onezone is a certified partner of the Global Industrial Relocation Network and holds liability insurance of €2,000,000 per claim (Allianz).

More on the service: production line relocation. Project photos: references. Documents: certifications. To discuss a move, contact us.

Frequently asked questions

When should the electrical survey take place?

As early as possible, while the line is still running and the people who know it are available. The survey data is needed to prepare the new site and to plan the work, so it should be finished before the relocation date is fixed.

Who is responsible for backing up PLC and drive programs?

Usually the plant owner, the machine builder or the integrator. The electrical subcontractor should ask for confirmation that backups exist, because the line cannot be put back into operation without them.

Can cables be reused after a relocation?

Cables that travel with a machine module and are undamaged are usually reconnected. Cables between machines often have to be replaced because the new layout needs different lengths and routes. Damaged cables should be replaced, not patched.

Which tests are carried out after reconnection?

Typically protective conductor continuity, insulation resistance, phase sequence and motor rotation, safety functions such as emergency stop, input and output checks and a functional run. The exact scope comes from the machine documentation, the applicable standards and the plant's procedures.

Does the electrical subcontractor also do the rigging?

Not necessarily. Many relocations use a specialised rigging company. What matters is a written interface: who releases each module, who removes cables fixed to the building and who protects cabinets and cable ends during transport.