Relocating a European Production Line to the USA: Electrical Points to Plan
A European production line cannot simply be reconnected in an American plant. The supply runs at 60 Hz instead of 50 Hz and at different voltage levels, US workplace rules expect electrical equipment to be approved – usually through listing by a recognised testing laboratory – and installation follows US codes such as NFPA 70 and NFPA 79. These points need to be settled before the line leaves Europe.
01 / Article
When a European production line moves to the USA, the electrical questions fall into four groups: the different supply, the approval of equipment under US workplace rules, the US codes for installation and machine wiring, and the practical planning of work in two countries. This article describes each group as of 20 November 2026 and points to the official sources. It is not compliance advice: what applies to a specific line is decided by the plant's engineering team, the machine builder and the local authority having jurisdiction.
Why can a European line not simply be plugged in?
The US Department of Energy summarises the difference: the United States uses 110–120 V at 60 Hz, while many other countries use 220–240 V at 50 Hz. Industrial plants also distribute three-phase power at voltage levels that often differ from the 400 V common in Europe, so the actual service voltage of the new building has to be confirmed early.
What this means in practice depends on the line, but typical questions are:
- Motors: a motor's speed depends on supply frequency, so motors fed directly from the mains run faster at 60 Hz. The machine builder decides whether motors, gearboxes or settings must change.
- Drives and power supplies: many frequency converters and power supplies accept a range of inputs, others do not. Each device needs to be checked against its data sheet.
- Transformers: some projects keep the European voltage inside the line and add a transformer; others convert the line to the local voltage. This is an engineering decision with consequences for approval and documentation.
- Component ratings: protective devices, cables and terminals have to suit the new voltage, current and available fault current.
What do US workplace rules say about electrical equipment?
In the USA, the Occupational Safety and Health Administration (OSHA) regulates electrical safety in workplaces. Its general industry standard states in 29 CFR 1910.303(a) that conductors and equipment "shall be acceptable only if approved". The definitions in 29 CFR 1910.399 describe three ways in which equipment is acceptable:
- it is accepted, certified, listed or labelled, or otherwise determined to be safe, by a Nationally Recognized Testing Laboratory (NRTL) recognised under 29 CFR 1910.7;
- for equipment of a kind that no NRTL tests or certifies, it has been inspected or tested by another federal agency or by a state, municipal or other local authority responsible for enforcing the occupational safety provisions of the National Electrical Code, and found to comply with the NEC as applied in the standard;
- for custom-made equipment designed for a particular customer, the manufacturer has determined it to be safe for its intended use on the basis of test data that the employer keeps available for inspection.
OSHA's NRTL Program recognises private organisations that test and certify products to US standards. Each NRTL uses its own registered certification mark.
What is a field evaluation?
Equipment built in Europe often carries a CE marking but no US listing. One route described in the US system is an evaluation of the unlabelled equipment where it is installed. NFPA 791, Recommended Practice and Procedures for Unlabeled Electrical Equipment Evaluation, covers recommended procedures for evaluating such equipment for compliance with nationally recognised standards. Which route is used for a particular line, who carries out the evaluation and whether the local authority accepts the result are questions to settle with the plant before shipment, because they can change what has to be modified in Europe.
Which US codes and standards apply to the installation?
- NFPA 70, National Electrical Code (NEC): the code for electrical design, installation and inspection in residential, commercial and industrial structures. The edition in force and any local amendments depend on the location of the plant.
- NFPA 79, Electrical Standard for Industrial Machinery: according to NFPA, it addresses electrical hazards involving industrial machinery, from single-motor machines to complex automated manufacturing systems, and aims to protect operators, equipment, facilities and work in progress.
- The local authority having jurisdiction: permits, inspections and acceptance of the installation are handled locally. The plant usually knows the process and the contacts.
European machines are typically built to IEC/EN 60204-1. Differences between that standard and NFPA 79 – for example in wiring colours, conductor sizing or documentation – are best identified by the machine builder during engineering, not discovered during reconnection.
How do you plan the electrical work across two countries?
- Decide before dismantling: voltage strategy, approval route and required modifications should be fixed while the line is still in Europe and the people who know it are available.
- One set of records: the cable schedule, labels and photographs made during disconnection in Europe are the basis for reconnection in the USA. The same team, or at least the same records, should cover both ends.
- Prepare the US site: supply, cable routes and earthing need to be ready when the line arrives. Clarify which work has to be done or signed off by locally licensed contractors.
- Interfaces: agree with the rigging company, the machine builder and the plant who disconnects, who ships and who reconnects each part.
- Travel and work authorisation: sending European technicians to the USA is a separate topic for the plant and its advisers and should be started early.
Which documents should travel with the line?
- updated schematics and cabinet layouts reflecting any modifications for the US supply;
- the cable schedule and photographs from disconnection;
- data sheets and certificates of the main components;
- test records from Europe and from the US site;
- any evaluation or inspection reports requested by the plant or the authority.
Our experience with US relocations
Onezone s.r.o. has worked on two production lines in the USA. For a vaccine production line moved from Germany to North Carolina, the team carried out the dismantling, electrical installation and reassembly of the technology; the line is installed in a cleanroom. For a CNC production line for the pharmaceutical industry in Florida, Onezone delivered the complete electrical installation, including mounting and connecting 16 control cabinets. Approvals and evaluations under US rules are a matter for the bodies described above.
More on the service: production line relocation. Both projects with photos: references. To plan a move, contact us.
Frequently asked questions
Does a CE marking count as approval in the USA?
OSHA's definitions refer to equipment that is listed, labelled or otherwise determined to be safe by a Nationally Recognized Testing Laboratory, or to the other routes described in 29 CFR 1910.399. A CE marking is not one of the routes named there.
What is an NRTL?
A Nationally Recognized Testing Laboratory is a private organisation recognised by OSHA under 29 CFR 1910.7 to test and certify products to US standards. Each NRTL uses its own registered certification mark.
What is the difference between NFPA 70 and NFPA 79?
NFPA 70, the National Electrical Code, covers electrical design, installation and inspection in residential, commercial and industrial structures. NFPA 79 is the Electrical Standard for Industrial Machinery and deals with the electrical equipment of the machines themselves.
Do motors need to be replaced when moving from 50 Hz to 60 Hz?
Not always. Motors fed directly from the mains run faster at 60 Hz, while motors on frequency converters may only need new settings. The machine builder should assess each drive and motor.
Can the same electrical team work in Europe and in the USA?
It helps, because the team that disconnects and labels the line knows it best during reconnection. Which work has to be done or signed off by locally licensed contractors, and the travel and work authorisation of technicians, should be clarified with the plant early.
Sources
- OSHA – 29 CFR 1910.303, General requirements, paragraph (a) Approval (checked 20 November 2026) osha.gov
- OSHA – 29 CFR 1910.399, Definitions applicable to Subpart S: Acceptable, Approved, Listed (checked 20 November 2026) osha.gov
- OSHA – Nationally Recognized Testing Laboratory (NRTL) Program (checked 20 November 2026) osha.gov
- NFPA – NFPA 70, National Electrical Code (checked 20 November 2026) nfpa.org
- NFPA – NFPA 79, Electrical Standard for Industrial Machinery (checked 20 November 2026) nfpa.org
- NFPA – NFPA 791, Recommended Practice and Procedures for Unlabeled Electrical Equipment Evaluation (checked 20 November 2026) nfpa.org
- U.S. Department of Energy – Electricity 101 (110–120 V at 60 Hz in the USA; checked 20 November 2026) energy.gov
02 / Related
Read on
Related services
03 / Contact
Contact Us Today
Our experienced team of electricians, mechanics, and technicians is ready to support your project with expertise and precision. Trust your electrical installation and assembly needs to professionals who prioritize quality, reliability, and a tailored approach. Contact us today!
- Samuel Stas, B.Sc. Owner & CEO
Responsible for international projects, client relations, and the coordination of our technical teams across Europe and the USA.
- Matúš Židuliak, B.Sc. Owner & CEO
Responsible for company strategy, business development, turnkey projects in Slovakia and the Czech Republic, and communication with clients.
- Martin Miksa Sales Representative
Responsible for communication with customers and business partners, as well as coordinating projects in Germany and Austria.